Main information:
• The Owner: North West Electric investment & development JSC
• Construction site: Suoi Chien town, Muong La district, Son La province
• Total investment: over 600 billion VND • Construction period: 2007 - 2009
• Hydraulic turbo-alternator: 02 turbo
• Installed capacity Nlm = 32MW
• Average of annual power production: 132 million KW
Scope of work of Song Da 5: Construction of reinforced concrete of dam, spillway, intake, sand discharge canal