LONG TAO HYDROPOWER PROJECT

I. Main Information

- The Employer: Long Tao Dien Bien JSC

- Location: Nam Muc river, Pu Xi ward, Tuan Giao district and Muong Muon, Na Sang, Huoi Mi wars, Muong Cha district, Dien Bien province

- Total Investment: 1.256 bil. VND

- Installed capacity: 42MW

- Number of units: 02

- The annual output: 189 mil. kWh

II. Scope of Song Da 5 works:

Foundation pit excavation of powerhouse, tailrace.

Total embankment and excavation volime: 511.690 m3, in which:

+ Soil excavation: 127.710 m3

+ Rock excavation: 383.980 m3

Construction period 03/2017– 12/2017