Main information:
• The Owner: Dakdrinh hydropower JSC (a part of PV Power corporation)
• Construction site: Son Tan town, Son Tay district, Quang Ngai province
• Total investment: 3.003 million VND
• Hydraulic turbo-alternator: 02 turbo
• Installed capacity : 125 MW
• Construction period : 2007 -:- 2011
Scope of work of Song Da 5:
- Construction of Spillway
- Exploitation and production of materials used for construction