Main information:
• The Owner: Power Construction JSC no.1
• Construction site: Duc Hanh town and Ly Bon town – Bao Lam district – Cao Bang province
• Total investment: around 276 billion VND
• Construction period: 2016 – 2018
• Installed capacity: 8 MW
• Hydraulic turbo-alternator: 01 turbo
• Average of annual power production: 33.42 million kWh.
Scope of work of Song Da 5:
Construction of entire main works