- The Employer: Power Construction No. 1 JSC
- Construction Location: Between Duc Hanh Commune, Bao Lam district, Cao Bang Province and Niem Tong Commune, Meo Vac District, Ha Giang Province.
- Total Investment: ~ VND 2000 billion
- Installed capacity: 46 MW.
- Number of units: 02
- The annual output: 192.175 million kWh
- Construction time: 2015-2017
- Foundation excavation for main works: Powerhouse, Tailrace, Power Station, Spillway, Main Dam, Diversion Culvert, Switch yard.
- Construction of Concrete structure for main works: Power house, Tailrace, Spillway, Main Dam, Diversion Culvert, Switch yard.
- Earth and Rock Excavation Quantity: 375.806m3 with the height of Excavation slope: 100 m.
- Total CVC Concrete quantity: 183,800,00 m3.
- The average construction rate: 11.000 m3/month.
- The maximum construction rate: 16.000 m3/month.